Change order form for subcontractors

Use it once the subcontractor and contractor agree on a change to the work. Signing it confirms every term — including any change to the subcontract sum and the contract time.

Amends the subcontract
Changes the contractor–subcontractor agreement, not the prime contract.
Use it when both parties agree
Subcontractor and contractor have settled the terms of the change.

Get the template

Free to download. Fill in your details to get the form.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
Subcontract

Change Order

Change order no.
007
1
Contract and change
Project
Riverside Medical Centre
Contractor
Tremblay Construction Ltd.
Date
Mar 19, 2027
Subcontractor
Northline Electrical Ltd.
Subcontract no.
SC-26-041 · Electrical
Subcontract date
Jul 8, 2026
The subcontract is changed as follows
Relocate panel LP-3B and add two 20 A circuits to suit the revised stair core layout, per Contractor’s Change Order 014 and Architect’s Drawing A5.3 Rev A.
2
Subcontract sum
Original subcontract sum
$612,000.00
Net change by previous change orders
$18,750.00
Subcontract sum prior to this change order
$630,750.00
Increased by this change order
+$14,860.00
New subcontract sum, including this change order
$645,610.00
3
Contract time
Changed by this order
+3 days
Substantial completion, before
Jul 14, 2027
Substantial completion, now
Jul 17, 2027
4
Signed by both parties
Subcontractor
Signature · date
Contractor
Signature · date
Illustrative example · sample figures
What’s on the form

One sheet. Every term both signers agree to.

1
Contract and change
Project, both parties and dates, plus a plain description of the change.
2
Subcontract sum
Original subcontract sum, prior changes, this change and the new sum in one column.
3
Contract time
Days added or removed and the revised substantial completion date.
4
Two signatures
Subcontractor and contractor sign. Once signed, the change binds the subcontract.