Sort overhead cost in construction examples into job-site and company overhead, then follow an illustrative 40-person contractor from overhead budget to bid.

Your overhead percentage sets the markup on every bid you send, and it is only as accurate as the costs you sort into it. A superintendent's truck booked to the office, equipment insurance filed as general and administrative (G&A), a project manager's salary split by habit: each choice moves money between job cost and overhead. The overhead rate changes, and so does every price built on it.
The error compounds. Randy Blount, former owner of Blount Contracting, describes a conversation he has with contractors regularly:
"Oh man, my overhead's 18%. And I'll say, 'Well, what's your gross profit margin?' Like it's around 34% or something. Like, 'Okay. Well, you're not 34% gross profit and you're also not 18% overhead.'"
- Randy Blount, former owner of Blount Contracting, on the CONEXPO-CON/AGG Podcast
In his example, about 10 points of that "overhead" belong at the job level. Jobs look 10 points more profitable than they are, and the company marks up new work on a rate that measures the wrong thing. When volume drops, the real fixed overhead goes unrecovered, and nobody notices until year-end.
This article sorts overhead cost in construction examples into three buckets, gives a rule for the grey-area costs, and follows one illustrative 40-person contractor from its overhead budget to a bid and then to a mid-year recovery check. Benchmarks come from Statistics Canada and the Construction Financial Management Association (CFMA).
Overhead cost in construction is any cost of running the company that you can't trace to the work on a single job. Accountants split construction costs into three buckets, and the split decides how each cost gets recovered.
The table below shows the three buckets and how each one reaches the client's price.
| Bucket | What it is | How it gets recovered |
|---|---|---|
| Direct costs | Labor, materials, subcontracts and equipment used to build the work | Estimated line by line in each bid |
| Job-site overhead (general conditions, indirect job cost) | Costs that exist because a project exists but don't belong to one task | Estimated and coded to the job, like any other cost |
| Company overhead (G&A, or SG&A in US reporting) | Costs that keep the business running whatever jobs are active | Added to bids as a markup |
Blount explains why the line between the second and third buckets matters:
"SG&A from GAAP, Generally Accepted Accounting Principles, should never be charged to a job. They should show up after gross profit."
- Randy Blount, former owner of Blount Contracting, on the CONEXPO-CON/AGG Podcast
Job-site overhead belongs in the job's budget and gross profit. Company overhead sits below gross profit and gets recovered through markup. With that split in place, sorting individual costs becomes straightforward.

The examples below cover the costs most contractors carry, each placed in the bucket it belongs in. Use them to check your chart of accounts line by line.

Job-site overhead is any cost created by a specific project that isn't part of one scope of work. Common examples include:
Company overhead is any cost you pay to keep the business open, whether you have two jobs running or twenty. Common examples include:
Statistics Canada publishes what several of these lines cost as a share of revenue. According to Statistics Canada's Financial Performance Data for construction (NAICS 23, 2024), average costs for businesses with $30,000 to $5 million in revenue were:
| Expense line | Share of total revenue |
|---|---|
| Rent | 2.0% |
| Professional and business fees | 1.9% |
| Insurance | 1.4% |
| Utilities and telephone | 1.2% |
| Advertising and promotion | 1.0% |
These figures come from firms smaller than most 20 to 60 person contractors. Use them to sanity-check individual lines, not as a total overhead target.
If you can trace a cost to a job through time records, a log or a usage record, charge it to the job. If you can't, it is company overhead. If it is mixed, split it on a written basis you apply every month. Remodeler George Cleary uses the same test:
"Anything that has the guy's time or fuel time for a vehicle going to a job is allocated to that particular job and therefore is not overhead."
- George Cleary, remodeler, in a Professional Remodeler roundtable
The table below applies that rule to the costs teams argue about most.
| Cost | Where it belongs |
|---|---|
| Project manager across several jobs | Job cost by timesheet hours, remainder to overhead |
| Superintendent's truck | Job cost by mileage or days on site |
| Small tools and consumables | Job cost when issued to a job, otherwise indirect allocated monthly |
| Equipment insurance, depreciation and mechanics | Equipment cost, charged to jobs through equipment rates |
| Estimators and unsuccessful bids | Company overhead |
| Warranty work | Its original job if open, otherwise company overhead |

Some costs aren't overhead at all. Materials are direct costs. Loan principal is a balance sheet item. Only the interest and depreciation reach the income statement, as Blount points out. Income tax comes after profit.
Writing these rules down matters most during a system change. Cindy Kleger, Controller at All States Construction, asked peers on the CFMA Connection Café for guidance on "what really is considered a job cost" while migrating to new software and rebuilding her chart of accounts.
Once costs sit in the right buckets, the company overhead total becomes a number you can price from.
Divide your annual company overhead budget by planned revenue or planned direct cost to get an overhead rate, then add that rate and your profit target to each job's direct cost. The example below uses illustrative figures in Canadian dollars for a 40-person Ontario general contractor.
The company's annual overhead budget looks like this:
| Overhead line (illustrative) | Annual budget |
|---|---|
| Office and admin salaries | $1,050,000 |
| Payroll burden on office salaries | $190,000 |
| Office rent and utilities | $150,000 |
| Corporate insurance | $90,000 |
| Software and IT | $80,000 |
| Accounting and legal | $70,000 |
| Marketing and business development | $60,000 |
| Office vehicles | $45,000 |
| Other | $55,000 |
| Total | $1,790,000 |
The company plans $16,000,000 in revenue and a 5% profit of $800,000. That leaves $13,410,000 of planned direct cost, including job-site overhead.
The same overhead gives two different rates depending on the base:
Both are correct. State the base every time you quote an overhead percentage, or you'll compare numbers that measure different things.
Now the company prices a job with $1,200,000 of direct cost. The markup on cost that recovers overhead and profit is ($1,790,000 + $800,000) ÷ $13,410,000 = 19.31%. Applied to this job, that adds $1,200,000 × 19.31% = $231,767, for a bid of $1,431,767. Overhead and profit make up 16.19% of that price, which is the margin. Use the Buildend markup and margin calculator to convert between the two.
A borrowed "cost plus 10%" prices the same job at $1,320,000, which is $111,767 lower. That bid doesn't cover this company's overhead, let alone its profit.

To compare your rate with peers, use a published benchmark with a clear definition. According to the CFMA 2026 Construction Financial Benchmarker executive summary, SG&A averaged 11.2% of revenue across 1,359 US contractors in fiscal 2025, 9.2% for Best in Class firms and close to 15% for specialty trade contractors. SG&A excludes job-site overhead, so compare it with your company overhead bucket only.
This bid only recovers overhead if the revenue plan holds. Dave Jurinic describes the same dependency:
"I have to account for these costs and set an annual budget. I then have to predict how many renovations and custom homes I will build that year so that I can apply these costs on every project above the actual construction and management costs."
- Dave Jurinic, Director of Operations at Toronto Custom Concepts, on RenoMark
That forecast is the weak point, and it is why the next check matters.
Compare the overhead you have recovered through billed work with the overhead you have actually spent, every month. The same illustrative contractor runs this check at June 30:
| Mid-year check (illustrative) | Amount |
|---|---|
| Planned revenue, January to June | $8,000,000 |
| Revenue billed, January to June | $6,400,000 |
| Overhead recovered at 11.19% of revenue | $716,000 |
| Overhead spent (half of the annual budget) | $895,000 |
| Under-recovered overhead | $179,000 |
Revenue is 20% behind plan, but most overhead is fixed, so the company is $179,000 short with six months left. If billing stays behind plan, the gap keeps growing at the same rate.

The response follows three steps:
Contractors who skip this check find the gap at year-end. Bob DuBree of Creative Contracting cut overhead from about $450,000 to about $150,000 over the same January to November period a year apart, after work dried up in the 2008 downturn. He also names the opposite problem:
"When you get busy, you get fat. You get fat on the overhead side."
- Bob DuBree, Creative Contracting, in a Professional Remodeler roundtable
Run a creep check once a year as well. Compare each overhead line with last year's, the same way you track a project budget, and compare overhead growth with revenue growth. A new office, new hires or new software raise the rate permanently. Both checks depend on one thing: the numbers in the job budget and in accounting have to describe the same costs.
Use the same cost codes in estimating, field coding and accounting, and control who can move a cost between a job and overhead. If the estimate codes job-site overhead one way and accounting files it another way, you can't compare estimate with actual, and the overhead rate drifts.
Custom builder Jeremy Sloane puts the cost of getting this wrong in plain terms:
"If that money is in the wrong bucket, I could be off when I budget a job by thousands and thousands of dollars."
- Jeremy Sloane, Sloane Construction Company, on Adaptive's Builders, Budgets & Beers
Three practices keep the buckets consistent:

Buildend supports this workflow. Buildend job costing uses the same cost codes for budgets and financial records, shows budgets, commitments and projected cost in one project view, and has configurable approval workflows and permissions. Your accounting system stays the system of record through integrations with QuickBooks Online and Desktop, Sage 100 and 300, and Yardi. Company overhead stays in accounting, and job-site overhead sits in the job budget where project teams see it.
Overhead cost in construction is any cost of running the company that you can't trace to one job, such as office rent, admin salaries, corporate insurance and accounting fees. Job-site costs like the trailer and superintendent belong to the job.
According to the CFMA 2026 Benchmarker, SG&A averaged 11.2% of revenue for US contractors in fiscal 2025. Specialty trades ran close to 15%. These figures exclude job-site overhead.
A good overhead percentage is one your bids fully recover at your actual volume. Compare your rate with your own plan each month before comparing it with a benchmark, and state the base you divide by.
Overhead cost in construction examples are only useful once each one sits in the right bucket. Sorting job-site and company overhead correctly gives you a true overhead rate. Pricing from your own overhead budget gives you a markup that covers it. A monthly recovery check tells you whether volume is keeping up.
Start today with one step: pull last year's income statement and mark every expense line as direct, job-site overhead or company overhead using the rule above. Recalculate your overhead rate from the company overhead lines only, then compare it with the markup in your current bids.