Calculate percent complete with cost-to-cost and line by line on the schedule of values, then reconcile the gap before it reaches your WIP and over/under billing.

Your project manager says the job is 50% complete. The cost report says 50% too. Then you walk the electrical room and find a $400,000 switchgear package still crated on pallets. That cost is in the job, but none of it is installed, so the 50% claims work nobody has built yet.
That one percentage sets earned revenue, over or under billing, and the gross profit your surety, your bank and your auditors read every quarter. An overstated percentage books margin early. The correction lands later, usually as fade near the end of the job.
"If you are 90% of the way complete on cost and 40% of the way complete on labor hours and quantity, somebody overspent somewhere."
- Josh Bohlke, CFO of an electrical contractor, on the Finance at the Jobsite podcast
This guide shows how to calculate percentage of work completed in construction two ways: cost-to-cost from your accounting data, and line by line on the schedule of values from the field. It then gives you a check to reconcile the two numbers and turns the agreed figure into one WIP row you can defend. Every figure below is an illustrative example from one fictional $2.4 million commercial job.

Divide the cost incurred to date by the total estimated cost of the job, then multiply that percentage by the current contract value to get earned revenue. Both inputs come from your job costing records: cost to date from posted invoices and payroll, and total estimated cost from the current budget plus the PM's estimate to complete.
The illustrative job starts with these figures:
| Item | Illustrative example |
|---|---|
| Current contract value | $2,400,000 |
| Total estimated cost | $2,000,000 |
| Cost incurred to date | $1,000,000 |
| Percent complete (cost-to-cost) | $1,000,000 ÷ $2,000,000 = 50% |
| Earned revenue to date | 50% × $2,400,000 = $1,200,000 |
| Gross profit to date | $1,200,000 − $1,000,000 = $200,000 |
Cost-to-cost is the default because the inputs already sit in your accounting system. That convenience is also its weakness.
Cost-to-cost treats every dollar spent as a dollar of work put in place. Five kinds of cost break that assumption:
The accounting standard addresses the first one directly. Under ASC 606-10-55-21, a contractor using a cost-based input method excludes costs that do not depict its performance, such as uninstalled materials that meet four stated conditions. On the illustrative job, $400,000 of the $1,000,000 cost to date is that crated switchgear. Accounting cannot see that from the cost report alone, so you need a second number that comes from the field.
Measure physical progress on each schedule of values (SOV) line with the method that fits that scope, weight each line by its scheduled value, and add the results. A single job-wide percentage hides which scope is ahead and which is behind.
"It's a one line, we are 50 % through with the project schedule of values. Well. That's a lot harder to verify than breaking it out by building, by level, by unit, by scope."
- Michael McKeon, Project Manager at Nordby Construction, on the Finance at the Jobsite podcast
Each method below fits a different kind of scope. Use the most objective method each line allows, and save supervisor estimates for lines too small to count.

The illustrative job's SOV, measured in the field, rolls up to $906,000 of earned value on a $2,400,000 contract, or 37.75%.

The field says 37.75%. Accounting says 50%. Electrical shows why: the switchgear milestone (25% of that line) earns nothing until the gear is set.
A 12-point gap is too large to sign. The next step is finding out where it comes from.
Compare the two percentages every month, and trace any gap above your threshold to a specific cause before you choose which figure to report. The gap is information. Each cause points to a different correction.
"The final, most important number is percent complete. Is the job physically as complete as the numbers show?"
- Kevin O'Shea, President and CFO of Shamrock Electric, in CFMA's Member Two Cents column
Work through the check in this order:

On the illustrative job, step 2 closes the gap. Excluding the $400,000 switchgear from both the numerator and the denominator gives ($1,000,000 − $400,000) ÷ ($2,000,000 − $400,000) = 37.5%. If the switchgear meets the ASC 606 conditions, you recognize revenue equal to its cost at zero margin: 37.5% × ($2,400,000 − $400,000) + $400,000 = $1,150,000 earned. Cost now says 37.5% and the field says 37.75%. The two numbers agree, so you sign.
Step 5 is where most WIP reviews stall. CFOs report the same pattern on CFMA's member forum:
"A good portion of this is PM's sandbagging their projections."
- Mark Windham, CFO of Brasington Bailey Construction, on CFMA Connection Cafe
Revise total estimated cost as soon as the PM's estimate changes, and book the cumulative effect in the current month. On the illustrative job, a $100,000 increase in estimated cost takes the adjusted percentage to $600,000 ÷ $1,700,000 = 35.3%. Earned revenue drops to $1,105,882, so this month absorbs a $44,118 reduction. A construction budget tracking routine that separates committed cost from actual cost catches these increases earlier.
If total estimated cost exceeds contract value, the job is a loss contract. Under ASC 605-35-25-45, you recognize the entire anticipated loss in the period it becomes evident.
Once you have a percentage you trust, it becomes the basis for the number your surety reads first.
Subtract earned revenue from billings to date: a positive result is overbilling (a liability), and a negative result is underbilling (an asset). The same sign convention runs down every row of a WIP schedule.
The illustrative job has billed $1,300,000. Correcting the percentage from 50% to 37.5% lowers earned revenue to $1,150,000, raises overbilling from $100,000 to $150,000 and cuts gross profit to date from $200,000 to $150,000.

Sureties and banks read that overbilling line closely, because it sets the bonding capacity they extend.
"I have to meet every year with our underwriter from our bonding to go through jobs on the WIP and why did we lose or gain?"
- Jennifer Murphy, CFO of Pleune Service Company, on the Finance at the Jobsite podcast
For the pay application that follows from these numbers, see Buildend's construction progress payments example, and use the construction retainage calculator for the amount withheld.
These rules shape how your percentage is used in financial statements and tax returns:
Getting one month right is useful. Getting every month right needs a routine.
Run the same two-number check every month in one sheet, with a named owner for each input and an approver for every override. Consistency matters more than the method you choose.
Build one row per SOV line with these columns:
| Column | Contents | Formula |
|---|---|---|
| A | SOV line | Text |
| B | Scheduled value | Input |
| C | Measurement method | Text |
| D | Line % complete (field) | Input from PM |
| E | Earned value (field) | =B2*D2 |
| F | Cost to date | From accounting |
| G | Uninstalled materials in cost | Input from PM |
| H | Estimate to complete | Input from PM |
| I | Line % complete (cost) | =(F2-G2)/(F2-G2+H2) |
| J | Gap | =D2-I2 |
| K | Review flag | =IF(ABS(J2)>0.05,"Review","") |
Total field percent is =SUM(E:E)/SUM(B:B). Keep last month's sheet untouched so you can compare cumulative percentages month to month.

Assign each input to one person:
Override control is where spreadsheets break. Robin Thomas, Director of Project Accounting at The Beck Group, put the question to peers on CFMA's member forum: if operations can input overrides, "how is that information reviewed or approved with Accounting before the financials are closed?"
In a spreadsheet, the answer is often an email thread. Buildend's job costing separates actual costs, commitments and cost to complete for each cost code, and lets you configure approval workflows and permissions on financial records. Its payment application workflow reviews progress billing against the commitment in the same platform, inside Buildend's wider construction financial management software.
Percent complete is two numbers. When you calculate percentage of work completed in construction from both the field and the cost report, the gap between them tells you what to fix before the WIP goes out.
Pick your three largest active jobs. For each one, have the PM measure every SOV line, pull cost-to-cost from accounting, and list any job where the gap exceeds 5 points. Trace each flagged gap through the six checks above before you sign.